Street repair and Customer Service's Duncan

From City Manager Wendell Johnson*

City Streets Improvements Project

The City Staff has completed the detailed work description and cost projections for all “Priority 1” street upgrades.

The priority 1 designation applies to those streets, which are in the very worst condition, based upon needed repairs and community “level-of-service” impact. There are 11 priority 1 streets as follows:

Street Name                 Repair Cost
Pearce Lane                        $6,820
Brown Street                     $23,100
Broadway Avenue              $55,660
Chestnut Avenue               $36,960
Hendrick Way                    $17,500
Long Street                       $96,470
Early Street                       $38,940
Grandview Avenue             $25,200
Laurel Lane                       $22,770
Florida Gateway Drive       $163,900
Biscayne Glynn                  $61,160

The City Public Works Staff and contractor will complete cost projections for the 36 “Priority 2” streets by July 22, 2011.

Within the limits of available funding, it is anticipated that approximately 12 priority 2 streets will be repaired for a total project cost of approximately $1,000,000.

The improvements to these streets will be paid from Sales Tax Bond Revenue and will be apparent to the citizens in these neighborhoods. The Final project list will be presented to the City Council on August 1, 2011 for consideration and approval.

The work is projected to commence during the first week in August.

This week from the staff reports. Some interesting facts.

Customer Service (Donna Duncan):
 
Phone Calls Taken............................422
Walk-up Customers Assisted..............905
Number of Payments Collected.........1842
Bills Generated................................2048
Taps Processed.....................................1
Total Payments Received...... $219,318.00

 Service Orders Generated:
     Field Service Orders..................297
     Severn Trent................................3
     Verify Shut-Offs..........................61
     Cut Off Non Pay..........................47
     Turn Back On.............................40
 
Reads:
     Initial Read....................34
     Final Read.....................38

The City Staff Report is available in pdf format here

This work by the Columbia County Observer is licensed under a Creative Commons Attribution-Noncommercial 3.0 United States License.

 
 

Make a comment • click here •
All comments are displayed at the end of the article and are moderated.

 

Read the City Manager's 2010 Budget and Administrative Report • here.

 

City Staff Report
 • Week ending July 15, 2011

 

The April Activity Report showing all the current City projects is available here.

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 