The Lake City Project
Report on tap
Columbia
County, FL (Posted May 07, 2011 06:10 am )
by City Manager Wendell Johnson and
staff
From City Manager Wendell Johnson
Highlights for this month are:
Kicklighter Road
WWTP: The design process
in on schedule and design drawings are at 90%.
Consulting Engineer, Hatch Mott MacDonald
Inc., will provide a design update presentation
to City Council on May 16, 2011.
General Aviation
Air Terminal: Thus far, $1,122,100 has
been expended on the projected budget of
$2,702,875. The terminal is expected to be
completed by August 2011.
FY 2011 Capital
Projects Schedule: As of April 2011,
the City is nearly 40% complete on the annual
Capital Projects Schedule. Thus far, $3.5
million has been expended of the approximate $9
million budget. The pace will pick up rapidly
during the next 5 months.