Lake City Report -
April 8, 2011
The Lake City Project
Report on tap
Columbia
County, FL (Posted April 08, 2011 11:05 pm )
by City Manager Wendell Johnson and
staff
From City Manager Wendell Johnson
Highlights for this month are:
Kicklighter Road
WWTP. City Staff and Hatch Mott McDonald
representatives met on March 29, 2011 to review
90% preliminary design drawings. The design
process is proceeding on schedule as expected.
General Aviation
Air Terminal. Construction continues on
schedule with a projected June 27th completion
date. Contractors have completed paving of the
U.S. 90 entrance road, the east parking lot with
fencing and an electronic vehicle gate.
Installation of metal roof decking continues
along with interior plumbing, wiring conduit,
and wall framing items which are partly
completed. Repaving of portions of the east
parking lot is completed.
As of this report,
$646,681 has been expended on the projected
budget of $2,702,875.
Community
Redevelopment Area Plan Update. City
Council Ordinance No. 2011-2010, once adopted,
will expand the boundary based on information
provided in the Finding of Necessity. The Final
Reading will be considered for approval by the
Council on April 18, 2011. Once the Finding of
Necessity is approved the expanded boundary will
be incorporated into the Redevelopment Plan.
The Public Workshop schedule will continue in
April 2011 and the Redevelopment Plan Draft
presented in May of 2011.