From City Manager Wendell Johnson
Airport
Terminal
The new terminal is well underway and the
Project Superintendent is on site managing Phase
I of the four-phase construction project.
The Phase I parking lot, retention pond, and
building pad excavation projects are proceeding
smoothly and on schedule.
Personnel Policy Manual
The “legal sufficiency” review of the new
Personnel Policy Manual was completed this week
by Marks Gray, P.A.
The Policy Manual represents a total revision
and supersedes the City’s existing “Employee
Handbook” dated March 20, 1995.
The new Manual provides updated and legally
sufficient policies and procedures relating to
general working conditions, job classifications,
pay, recruitment, probationary periods, duty
standards, leaves, training, records,
evaluation, benefits, disciplinary, complaint
and separation actions.
The new Manual will be presented for
consideration of the City Council on November
15, 2010 and if approved, will be immediately
implemented.
The City Staff Report is available in pdf format
here.