Lake City Report - May 6, 2011
The Lake City Project Report on tap

From City Manager Wendell Johnson

May 2011 Project and Activities Report

Highlights for this month are:

Kicklighter Road WWTP:     The design process in on schedule and design drawings are at 90%.   Consulting Engineer, Hatch Mott MacDonald Inc., will provide a design update presentation to City Council on May 16, 2011.  

General Aviation Air Terminal:  Thus far, $1,122,100 has been expended on the projected budget of $2,702,875.   The terminal is expected to be completed by August 2011.

FY 2011 Capital Projects Schedule:   As of April 2011, the City is nearly 40% complete on the annual Capital Projects Schedule. Thus far, $3.5 million has been expended of the approximate $9 million budget.  The pace will pick up rapidly during the next 5 months.

The City Staff Report is available in pdf format here.

This work by the Columbia County Observer is licensed under a Creative Commons Attribution-Noncommercial 3.0 United States License.

 
 

Make a comment • click here •
All comments are displayed at the end of the article and are moderated.

 

Read the City Manager's 2010 Budget and Administrative Report • here.

 

City Staff Report
 • Week ending May 6, 2011

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

     • Fair Use Policy     • Privacy                              © ColumbiaCountyObserver.com